On Fri, Feb 09, 2007 at 06:25:15PM +1300, Paul Eggleton wrote:
> BTW what happens after the freeze date, ie. presumably there is a period where
> we test and then release? If so when is the proposed release date?
I propose something like that. I say that the test period be no shorter
then 1 week, but it will not end until all bugs attached to the release
have either been detached or closed. Since two of them have no patches,
I suspect that the test cycle could last a little more then two weeks. I
would like to tag and release by Monday 2007-03-05.
If anyone wants to go through the logs and update the ChangeLog you will
be my Best Opie Friend. Otherwise I will get to it at the end of the
test cycle.
Anyone disagree or think the timetable is unreasonable, speak up.
E